πŸ“– Kahneman on the planning fallacyLiterature note
LITERATURE NOTE

πŸ“…Kahneman on the planning fallacy

🚦 Status🟒 Processed
🏷️ Topics
PsychologyBusiness

🧡SYNTHESIS

Paraphrase, not quotation: chapters 23 and 24 of πŸ“• Thinking, Fast and Slow.

Kahneman tells a story against himself. He once led a team writing a school curriculum. After a year he asked everyone to estimate how long the rest would take; the answers clustered around two years. Then he asked a colleague who knew many such projects how they had gone. About four in ten had never finished, and the others had taken seven to ten years. The team heard this, felt deflated, and carried on. It took eight more years.

The inside view builds a forecast from the plan in hand: these tasks, this team. The outside view ignores the plan and asks what happened to projects like this one. The inside view is not stupid, it is detailed, and the detail is what makes it convincing. It simply has no place for the things nobody has thought of yet.

His remedy: start from the reference class, then adjust.

✨KEY IDEAS

The curriculum team had the statistics in the room, from one of its own members, and did not use them.
The detail that makes the chapter. Knowing the base rate is not the same as believing it applies to you.
An inside-view forecast is a best-case scenario that feels like a realistic one.
My January plan had no line for the load test fails. It had a line for running the load test.
The fix is to find a class of similar past projects, take its distribution as the starting estimate, and adjust for what is truly different.
The outside view, attributed in the chapter to Bent Flyvbjerg's work on large projects.
Optimism is rewarded: the confident plan gets funded, and so organisations select for the planning fallacy.
Chapter 24. The Sales forecast and my date were both rewarded for being early.
A pre-mortem asks the team to assume the project has failed and write down why.
Gary Klein's method, at the end of chapter 24. We did one on 10 March, the day before launch, which is late to learn anything you can still act on.

πŸ“READING NOTES

Twelve days after the launch

I read these two chapters out of order, on purpose, because I wanted to know how wrong I had been and whether there was a name for it. There is: 🧩 Planning fallacy.

The facts of my own case

  • Planned launch: 18 February.
  • Recommended the slip: 12 February. See πŸ“œ Slip the launch from 18 February to 11 March.
  • Launched: 11 March. Three weeks late.
  • My estimate in December was built entirely from the task list. I can reconstruct it. Every item on it was true.

Inside view, outside view

Inside view Outside view
Question What do we still have to do? How did the last ones go?
Material The plan The record
Feels Specific, responsible Vague, slightly insulting
Misses Unknown unknowns What is special about this case

🧩 The outside view has the method. This afternoon I did the exercise I should have done in December: listed Halden's last eight launches against their first announced dates. I had been at the company for all of them. I had watched them be late.

The sentence I could not have written in January

My three weeks were better than the house average. I had been treating the slip as a failure of my planning. Against the reference class it is an ordinary result that I announced earlier than usual.

Where I think he lets us off too lightly

He presents the fallacy as a cognitive error. In an organisation it is also a negotiation. Joachim needed a date for his quarter; an honest range would have been heard as weakness. An outside-view estimate is not only harder to think, it is harder to say out loud. The chapter on optimism nods at this and moves on.

And the outside view has its own trap: choosing the reference class. Eight launches at one company is a small sample, and I chose which ones counted.

What I will do

  1. Every estimate I give starts with the record and says so.
  2. A range, with the middle named second.
  3. The pre-mortem stays, but its findings need an owner, or it is theatre.

What it produced

πŸ’Ž My launch estimates ignore every launch I have seen, written straight after the list of eight.

Added 26 September: used the outside view on myself for the promotion case: how long do these decisions usually take here, and how often is the first answer yes.

Questions it left me with

  • What is the right reference class for discovery work, where there is no launch to be late for?
  • If I give Joachim a range next time, what does he do with it? Is there a version he can put in a forecast?
  • The curriculum team carried on after hearing the numbers. Would I have slipped the launch in January if I had made the list of eight then? I do not think so, and that bothers me.

Related notes

Reading record

  • Section read: Chapters 23 and 24

πŸ—£οΈIN SHORT

  • In : Thinking, Fast and Slow, chapters 23 and 24
  • Kahneman argues that : plans are forecast from the inside, as best cases, and that the record of similar projects is a better starting point than any amount of detail about this one
  • by stating that : planners who knew the base rates still ignored them, that organisations reward optimistic plans, and that reference classes and pre-mortems are the practical correctives