🧩 The outside viewConcept
CONCEPT

🔭The outside view

🚦 Status🗂️ Library
🏷️ Topics
conceptmental_modelforecasting
❤️ Favorite⭐ Favourite

🧩EXPLANATION

Estimating from how things like this usually go, before looking at the details of this one. The method is sometimes called reference class forecasting:

  1. Name the reference class: projects of this kind, at this size, in this place.
  2. Find its record: how long they took, how often they failed.
  3. Start from that record. Adjust for the particular case only where there is a reason you could defend to a stranger.

It is the correction for the 🧩 Planning fallacy, and it comes from the same chapters of 📕 Thinking, Fast and Slow. My notes: 📖 Kahneman on the planning fallacy.

Often confused with: pessimism. It is not a mood. It is a different source of data. It also has a real weakness: choosing the reference class is a judgment, and a careless choice returns a confident wrong answer.

Where I have seen it

Halden's last eight launches. On 23 March I listed them against their first announced dates. I had been at the company for all of them.

  • Average: six weeks late.
  • Mine: three weeks late, and I had spent February feeling like the first person it had ever happened to.

The conclusion is its own note, 💎 My launch estimates ignore every launch I have seen.

Since then every date I give has the record of similar work beside it. When there is no record I call the estimate a guess, in that word, which is less popular than a date.

🔗LINKED FROM

🕸️CONNECTIONS

🧩 Planning fallacyPlanning fallacy📕 Thinking, Fast and SlowThinking, Fast and Slow📖 Kahneman on the planning fallacyKahneman on the planning …💎 My launch estimates ignore every launch I have seenMy launch estimates ignor…📰 Self-RelianceSelf-Reliance📰 Why software projects take longer than you thinkWhy software projects tak…The outside view