💎 My launch estimates ignore every launch I have seenPermanent note
PERMANENT NOTE

🔭My launch estimates ignore every launch I have seen

🚦 Status🌳 Mature
🪐 Cluster
PsychologyBusiness
🏷️ Topics
PsychologyBusiness
🔗 Connections
19hub
📅 Reviewed7 Dec 2025

💎CORE ARGUMENT

When I estimated the Exceptions Inbox launch I did what everyone does. I looked at this project: this team, these stories, this customer, the risks I could name. I added the pieces, added a margin for the risks, and arrived at 18 February. It felt rigorous. It was a view from inside, and the inside view contains no information about how projects like this usually go.

That information existed, down the corridor. After the launch I went back through eight earlier Halden launches. On average they had arrived six weeks after their first announced date. I had been present for several of them and had sat in their retrospectives. None of it had entered my estimate, because each of those launches came with a story about why it was special, and so did mine.

We slipped on 12 February and launched on 11 March, three weeks late. By the house average I did well. By my own estimate I failed. The second sentence is the misleading one: the estimate was the error, not the project.

What I do now is mechanical on purpose, since judgment is the faculty that fails here:

  1. Write the inside estimate as before.
  2. Find the reference class and its record: launches of this size, at this company.
  3. Start from the record, and move towards the inside estimate only for reasons I could defend to a stranger.

The uncomfortable part is social. An outside-view date sounds like pessimism, or like not believing in the team. I now think the reverse. Quoting a date that eight predecessors missed is the disrespectful act, because it sets the team up to be late against a number that was never real.

Where I might be wrong. Eight launches is a small sample, and I chose which eight after I already knew what I wanted them to say. Some were late for reasons that have since been fixed.

It also suits me. Everyone is six weeks late turns my three weeks into a success, and I notice how quickly I reached for it.

How this note changed

  • 23 March 2025: Written the morning after reading the chapter. Angry at myself, which shows.
  • 28 March 2025: Took the anger out. Added the three steps while closing the launch project.
  • 7 December 2025: Reread for issue 52. The social paragraph is the part I still find hard to act on.

🌍WHY IT MATTERS

Every date I give now comes with the record of similar work beside it. If I cannot find a record, I say the estimate is a guess, in that word.

☑️NEXT STEPS

  • Collect first-announced and actual dates for past Halden launches
  • Put the six-week average in the launch closing note
  • Give the Carrier Scorecards build estimate with its reference class
🧭 COMPASS
⬆️ North (Upstream)

The inside view and the outside view, read twelve days after the launch; and an essay on why the typical estimate sits well below the average outcome.

⬅️ West (Similar)
🎯 Center (Mechanism)

Planning from the details of the case at hand produces a best-case scenario with small adjustments. The distribution of outcomes for similar past cases is a better predictor, and it is ignored because each case feels unique from inside.

➡️ East (Opposite)

A date is also a tool. An ambitious one focuses a team, and a date padded to the historical average will be filled to the last day. The honest estimate and the useful deadline may be two different numbers.

⬇️ South (Downstream)

The slip itself, the issue that told it straight, and the closing note of the launch project.

📜 Slip the launch from 18 February to 11 March📝 Issue 34 - The estimate I gave and the one I should have📌 Close the launch project and write what I would change

🕸️CONNECTIONS

📖 Kahneman on the planning fallacyKahneman on the planning …📖 Bernhardsson on why projects run lateBernhardsson on why proje…💎 Late projects are late by a multiple and not by a marginLate projects are late by…💎 A number without its base rate is a storyA number without its base…02. 🎲 Decisions under Uncertainty02. Decisions under Unce…🧩 Planning fallacyPlanning fallacy🧩 The outside viewThe outside view🔬 Judgment under Uncertainty - Heuristics and BiasesJudgment under Uncertaint…🎙️ Cautionary TalesCautionary Tales📰 Self-RelianceSelf-Reliance📰 Why software projects take longer than you thinkWhy software projects tak…📕 Thinking, Fast and SlowThinking, Fast and SlowMy launch estimates ignor…